The Current Permit Timeline
This is the fourth time in four decades that some company or another has applied for a Preliminary Permit to study this VERY SAME PROJECT.
February 10, 2023: York Energy Storage applied for a preliminary permit for the project from the Federal Energy Regulatory Commission (FERC).
September 6, 2023: FERC rejected the permit, citing two deficiencies.
November 14, 2023: York Energy Storage reapplied for a preliminary permit.
January 5, 2024: FERC issued a Deficiency Letter.
January 15, 2024: York Energy Storage resubmitted to FERC.
February 1, 2024: FERC accepted the preliminary permit application and provided public notice of it. This began a 60-day window to file comments and interventions objecting to the project. Comments and interventions could be filed through March 31, 2024.
November 21, 2024: FERC granted York Energy Storage a preliminary permit to study the construction of a pumped storage facility at Cuffs Run along the Susquehanna River in York County.
December 18, 2025: Partners filed their opening brief with the U.S. Circuit Court of Appeals for the Third Circuit in an appeal of the Federal Energy Regulatory Commission’s decision to grant a preliminary permit for the Cuffs Run pumped storage project.
July 1, 2026: Oral arguments were held in the U.S. Court of Appeals for the Third Circuit as Lancaster Conservancy and our partners continue our appeal of the Federal Energy Regulatory Commission’s decision to grant a preliminary permit for a pumped storage facility at Cuffs Run.